丙烯酸球场对地面的基础要求

丙烯酸球场对水泥和沥青基础的要求
Acrylic stadium requirements for cement and asphalt base
   平整度:
Flatness:
   基础应具有一定的强度和稳定性。基础不能产生裂缝和由于冰冻引起的不均匀冻胀。平整度合格率在95%以上,3米直尺误差3mm。
Foundation should have a certain degree of strength and stability. The foundation can not crack and the uneven frost freeze induced. Flatness qualification rate in more than 95%, 3 meter ruler error 3mm.
   坡度:
Slope:
   横向<0.1‰,纵向<1‰,跳高区<4‰,表面应平坦光滑保证排水。
Lateral <0.1 ‰ <1 ‰, vertical jump, <4 ‰, the surface should be flat and smooth to ensure drainage.
   强度和稳定性:
Strength and stability:
   沥青基础最好采用不含腊,或含腊很少的沥青材料,其沥青混合料必须充分压实。表面均匀坚实,平整无裂纹,无烂边堆挤,无麻面,接缝平顺光滑。沥青混凝土面层碎石粒径为2—5mm,含油量5.8—6.4%,接合层碎石粒径为6—9mm,含油量4.6—5.8%。压实密实度不得小于95%,在中型碾压机压过后,无显著轮迹,无发软起皮,无浮土松散,波浪等现象。
Asphalt base the best use of non wax, or paraffin little asphalt, the asphalt mixture must be fully compacted. Uniformly on the surface of solid, smooth and no crack, no broken edge pile up, without pits, joint smooth. The asphalt concrete surface layer of gravel size is 2 5mm, the oil content of 5.8 - 6.4%, the bonding layer of gravel size is 6 9mm, the oil content of 4.6 - 5.8%. Compaction shall be not less than 95%, in medium rolling machine pressure after, no significant wheel track, no soft skin, no dust loose, wave phenomenon.
   排水:
Drainage:
   排水系统在大雨后二小时必需排出积水。
The drainage system in the rain after two hours required to discharge water.
   保养期:
Maintenance period:
   基础保养期28天。
Basic maintenance period of 28 days.