(1).施工前对地基检测,清理现场、放水,把积水部分画出来以备修补,把配料及搅拌场地准备好,保持配料场地及周围的干净,按工艺线画线,放施工线,白线盖住接缝。
(1). Before the construction of the foundation inspection, cleaning up the site, the water, the water part draw out for repair, the batching and mixing site ready, keep the ingredients site and nearby clean, according to the process line for line drawing, construction line, white cover joint.
(2).配料:严格执行公司技术部下达的工艺配方,准备计量各组分,搅拌均匀。所需工具:台称、配料桶、搅拌桶、搅拌机、开桶板子、钳子、刀子。
(2). Ingredients: strict implementation of process formulation technology company issued, for measuring components, stirring evenly. Required tools: say, batching, mixing barrel, barrel, barrel mixer board, pliers, knife.
(3).搅拌:浆料、黑胶粒按一定比例搅拌均匀,每组充分搅拌。
(3). Stir: pulp, black particles according to a certain proportion, mixing evenly, each fully mixing.
(4).摊铺:摊铺前应检查好地基是否平整,并做相应措施。施工次序由内向外,减少对成品的污染。
(4). Spreading: check whether the formation of good foundation should be before paving, and corresponding measures. The construction sequence from inside to outside, reduce product contamination.
(5).修边:接边部位由指定技术人员修整,在接硬边时,应根据坡度调整,在接软硬边时,应对硬边清理打磨,以保证粘接的牢固性。修边人员并随时检查厚度、平整度。
(5). Trimming: edge position specified by the technical staff in the dressing, hard edge, should be based on the adjustment of the slope, on the soft side, deal with hard edge cleaning and polishing, in order to ensure the firmness of the bonding. Trimming staff and at any time to check the thickness, roughness.
(6).面层:由指定技术人员操作,待底层干透、稳固后,将纯胶均匀喷涂于面层,厚度为1-2mm。
(6). The surface layer: designated by the technical staff, to bottom dry, solid, pure glue evenly sprayed on the surface layer, the thickness of 1-2mm.
(7).清理:待塑胶熟化好后收防滑颗粒,修边清理下一个工作面。按铺胶图要求把塑胶面层全部铺完,整体清理场地。
(7). Cleaning: after ripening after receiving plastic anti-skid particles, trimming and cleaning the next working face. According to shop glue plastic surface layer are paved, the whole cleaning the site.
(8).放线:按平面布置图放线。所需工具:钢尺50米(鉴定过)、经纬仪2″。
(8). Ray: according to layout lines. Required tools: the ruler 50 meters (identified), theodolite 2 ".
(9).喷枪:所需工具:喷线、喷枪、气泵。
(9). Lance: required tools: spray line, spray gun, air pump.