塑胶网球场施工及基础夯实

1、塑胶网球场施工基土压实密度达到95%,用14吨以上带振动压路机进行碾压,碾压保证含水率8-12%。
1, plastic tennis court construction soil compaction density reached 95%, road roller to roll 14 tons with vibration, compaction water content 8-12% guarantee.
2、在碾压跑道时,纵向沿跑道内边向外侧碾压,行车速度为25-30米/分,重叠碾压宽度不少于50cm。有条件时最好采用振动碾压机进行施工,一般碾压3-5编,如果发现簧土。
2, in the rolling track, longitudinally along the runway edge to the outer side of the rolling, speed of 25-30 M / min, overlap compaction width not less than 50cm. The best conditions when using vibratory roller compacted construction, general 3-5, if it is found that the spring soil.
3、塑胶网球场施工应及时向业主反映,在得到业主、监理等权威机构的同意前提下,可采用用石块挤压。
3, plastic tennis court construction should be timely to reflect the owners, the owners, supervision authorities agreed to the premise, can be used with a stone extrusion.
4、或用挖机挖出弹簧土后填实等方法,如果填不到原有标高需再加填压实,或超标高要开挖后压实。确保基础的压实密度达到95%。
4, or by digging out spring soil filling method, if not to fill the original elevation should be added to fill compaction, or exceed the standard high to excavation after compaction. Ensure that the compaction density reached 95%.