球场施工胶面铺设完成后,全场做好卫生清洁工作,完成后即可开始划线,其步骤如下:
Stadium, after the completion of construction of glue laid all do a good job in health clean can begin after the completion of the marking, the steps are as follows:
球场施工:http://www.yj0755.com
Golf course construction
⑴首先复检基本桩点,并对误差做调校确认后,按照国际田联的标准进行测量,画出各种标志线,以此为基准,用钢尺把各控制点位定出,用铁钉定点, 球场施工再用胶带沿点位铺贴出球场的各种范围。
(1) the first review the basic point, and error calibration confirmation, measure in accordance with the standards of the iaaf, draw a line signs, as a benchmark, the every control point set with steel rule, use nails fixed point, reoccupy adhesive tape along the stadium construction point the shop is stuck out of the range of the pitch.
⑵球场画线范围铺贴好后即可开始喷线,注意线槽底面一定要加一层5-8MMEVA泡沫垫层,使线槽与道面能更紧密地贴合而防止虚边。
Scope of diction pitch line drawing can begin after the shop is stuck spray line, pay attention to the trough bottom must add a layer of 5-8 mmeva foam cushion, trough and the pavement can fit more closely and prevent the virtual edge.
球场施工标志线喷涂注意事项
Stadium construction marker spraying matters needing attention
⑴划线后需经体育工艺员复核,对各部分线长度进行校核,直线部分用鉴定过的钢尺(包括尺长校正、温度校正)进行复核,确认符合后,方可按国际田联规定的彩色标志喷漆。
Subject to physical engineer check after (1) line, to check each part of the line length, straight with steel rule for the identification of a part (including feet long correction, temperature correction) for confirmation, after confirmation in accordance with, can press the iaaf rules of color painting.
⑵喷漆时,
球场施工要反复检查喷线木盒的宽度是否符合田联的规定,如不符合应及时调整。
2 spray paint, stadium construction double-check the width of the spray line box is in line with the iaaf rules, such as do not meet should timely adjust.