世界杯足球赛掀起新一轮的浪潮

世界杯拉来帷幕,吸引了无数球迷的,来自全世界的不同球队准备在球场上一决高下。球场施工这个话题也慢慢出现在大众的视线。
Begun on the World Cup, attracted numerous fans of different teams from all over the world to compete on the field. Stadium construction this topic also slowly appeared in public view.
虽为透气型塑胶地面,球场施工EPDM塑胶跑道也同所有运动地面一样,对地基有一定的要求,一个合格的EPDM塑胶运动地面,处理好地基是必须的。
EPDM is breathable plastic ground, stadium construction plastic runway, like all sports ground, also have a request for the foundation, a qualified EPDM plastic sports ground, handle the foundation is a must.
一,先在压实的素土基层上铺装一层厚150mm大碎石层(80-120mm)再在此基础上铺装一层100mm厚的小碎石层(40-80mm),把小碎石层用水冲压实后再进行混凝土基础层施工。
A, first in primary element of soil compaction on shop is a 150 mm thick gravel layer (80-120 - mm) and then on the basis of this small shop is a 100 mm thick layer of gravel layer (40-80 - mm), the small gravel layer water real concrete base layer construction of the reentry after stamping.
二,混凝土基础层在施工过程中要注意施工标准,基础层标准为120mm厚的C25混凝土组成,其基础左右倾斜度不得超过1:100,跑进方向的上下倾斜度不得超过1:1000。基础表面平整度以两米靠尺最低部分不超过3mm为标准,其表面应当原浆压实抹平为宜。然后进行20天的维护保养。
Two, the concrete base layer in construction process should pay attention to the construction standard, the standard for the base layer of 120 mm thick C25 concrete, about its basic gradient must not exceed 1:100, ran into the direction of the tilt up and down to no more than the latter. Based on surface roughness in the lowest part of no more than two meters by feet 3 mm for the standard, the surface shall be protoplasmic compaction screeding advisable. Then 20 days of maintenance.
球场施工:http://www.yj0755.com
Golf course construction
地基处理必须严格按照以上步骤执行,地基处理完成后就可以在上面进行EPDM塑胶地面施工了。
Foundation treatment must be in strict accordance with the above steps, after the completion of the foundation treatment can undertake EPDM plastic ground construction in the above.